Seacoast Utility Authority 29.5 MGD Water Treatment Facility
Start Date: October 2009 (EST.)
Completion Date: December 2010 (EST.)
Client: Seacoast Utility Authority
References: David Prah, P.E. @ Camp Dresser & McKee (561) 689-3336
Seacoast Utility Authority contracted with Reynolds Inc. to construct a new 30.5 million gallon per day (MGD) finished water treatment plant comprised of 26.0 MGD of nanofiltration (NF), 3.5 MGD of low pressure reverse osmosis (LPRO), and 1.0 MGD of pretreated local surficial aquifer blend water.
Aerex’s scope includes the shop manufacture of ten NF skids designed for a permeate flow of 2.6 MGD each, shop manufacture of two LPRO skids designed for a permeate flow of 1.75 MGD each, manufacture of all cartridge filter housings and 316L stainless steel off-skid piping.
The structural components of the Seacoast Utility... more 